St. John’s, Antigua, 18 November 2026 – The Antigua Public Utilities Authority (APUA) advises the public that unplanned island-wide power outages occurred on Tuesday, 17 November, at approximately 3:35 p.m., following an attempt to energise a transformer that exports power from the Blackpine Power Plant.
The process involved transferring power generation from one transformer to another as part of routine system management and checks. During the process, an issue developed with the outgoing 11 kV breaker, which exports power from the Blackpine Power Plant, and maintenance was required.

After maintenance on the circuit breaker was completed, an attempt was made to energise the transformer. An unforeseeable system collapse occurred, resulting in an island-wide power outage.
APUA, in collaboration with APC, immediately began efforts to restore electricity service after the fault was isolated. However, system challenges during restoration resulted in several interruptions as the system was progressively brought back online.

Restoration is a meticulous, coordinated process involving power plant technicians and system control operators. Generation must be carefully matched with the amount of electricity being used by customers to maintain system stability.
There was no shortage of generation capacity. However, challenges and delays arose while efforts were made to bring the LNG and other generation units online to support the restoration process. APUA and APC teams continued working to safely stabilise the system and restore service.

Electricity service was fully restored by approximately 7:00 p.m.
APUA recognises the inconvenience caused by the extended and intermittent outages and appreciates the public’s patience and understanding.
APUA and APC will conduct a detailed assessment of the events and the sequence in which they occurred. Following this assessment, measures will be put in place to strengthen the system and minimise the likelihood and duration of similar outages in the future.

APUA remains committed to maintaining a reliable electricity supply and to safely and efficiently restoring service when unplanned interruptions occur.